Contracts for Works and Works Supervision for the construction of the section Šićki Brod – Đurđevik - Lot 2 (Živinice Bypass)
In the presence of members of the Management Board of JP Ceste FBiH, the Contract for the supervision of works on the alignment and road structures, construction of the section Šićki Brod – Đurđevik, Tuzla – Sarajevo road (Lot 2) was signed today in Sarajevo.
The contract was signed by Ljubo Pravdić, Acting Director of JP Ceste FBiH on behalf of the Investor and Asim Demirović, representative of the JV Aik-Inženjering d.o.o. Banovići and PPG d.o.o. Sarajevo on behalf of the Contractor.
The Contract value is BAM 1.797.026, 40 (including VAT) while the contract period is 32 months. The contract will be financed from the budget of the FBIH Government.
Today's event was preceded by the signing of the Contract for Works on the alignment and road structures, construction of the section Šićki Brod – Đurđevik, Tuzla – Sarajevo road (Lot 2), at km 5+400 - km 11+250.
On behalf of the Investor, the Contract was signed by Ljubo Pravdić, Acting Director of JP Ceste FBiH on the one, and Hamzalija Ibrić, representative of the Contractor - JV Jata Group d.o.o. Srebrenik, Euro-Asfalt d.o.o. Sarajevo, HIH d.o.o. Živinice, Roading d.o.o. Gračanica, Rial-Šped d.o.o. Doboj Istok and Cestotehnik d.o.o. Tuzla, on the other side.
The construction of this section includes works on the alignment, facilities and bypasses with a length of 5, 85 km, drainage works, environmental protection and landscaping, works on traffic equipment and signalling, etc.
The contracted period is 30 months while the Contract will be financed from the budget of the FBIH Government. The Contract value is BAM 58.499.974, 04 (including VAT).