Contract for the construction of Bugojno Bypass

Under the FBIH Roads Floods Repairs and Upgrade Project, new Contract for the Construction and Reconstruction of Bypasses – Lot 1: M16.4 Bugojno, Construction of Bugojno Bypass (phase I) was signed today.

Contract for the construction of Bugojno Bypass thumb thumb

The contract was signed by the director of FBH Roads, Ljubo Pravdić and representatives of the Contractor - JV within Putovi d.o.o. Grude and Dobojputevi d.d. Doboj Jug.

The project includes the construction of the alignment with three roundabouts, total length 1925 m, service roads, drainage, lighting and traffic signalling.

Contract period is 12 months and the contract amount is BAM 4.528.639, 46.

Works supervision shall be carried out by the company Roughton Ltd.

The contract will be financed with the EBRD credit funds.